New Foundation – H-E-B Bread Plant Corpus Christi
Location: Corpus Christi, TX
Timeline: 4 Weeks
Description: Full civil services included:
- Saw cutting and removal of existing concrete to excavate for multiple electrical duct banks.
- Back-fill of completed electrical duct bank conduits in 8” lifts with select fill (per engineering specs (~450 tons)
- Installation of select fill grade beam subgrade for 2’ tall equipment pad. (~60 tons)
- Installation of 2’ tall formwork (~300 sf) and rebar (~700LF)
- Placement of concrete (~80CY’s)
- Removal of formwork and final site clean-up.